City of Menominee – State Revolving Fund Water & Sewer Utility Project Update

Week of September 6th

The contractor continued to pour sidewalk, driveways, and curb ramps throughout the project; crews finished grading, shaping, and placing gravel along 16th Avenue; and crews continued to place topsoil and final landscape at various locations throughout the project.

Week of September 12th

The contractor will continue to pour sidewalk, driveways, and curb ramps throughout the project; crews will place curb and gutter along 16th Avenue; crews will continue to place topsoil and final landscape where possible, and crews will continue water service replacements throughout the City.

PLEASE NOTE

  • As the concrete sidewalk and driveway aprons are poured, please stay off them for at least 7 days to allow the concrete to fully cure.