City of Menominee – State Revolving Fund Water & Sewer Utility Project Update

Week of October 3rd

The contractor continued to pour sidewalks, driveways, and curb ramps along 16th Avenue; crews placed topsoil and landscaped where possible; and teams completed water service replacements at various locations throughout the City.

Week of October 10th

The contractor will complete pouring sidewalk, driveways, and curb ramps along 16th Avenue; crews will continue to place topsoil and final landscape where possible; crews will begin final shaping of the gravel surfaces in preparation for asphalt, and teams will continue water service replacements at various locations throughout the City.

PLEASE NOTE

  • As the concrete sidewalk and driveway aprons are poured, please keep your children and pets away from the fresh concrete for a couple of days to avoid damaging the surface.
  • Do not drive on the driveways for at least 7 days to allow the concrete to cure fully.
  • Please keep everything off the newly seeded topsoil areas, seedlings are in a vulnerable state as the grass begins to grow.
  • Asphalt paving is currently scheduled to begin mid-October and expected to take approximately one week, weather dependent.