City of Menominee – State Revolving Fund Water & Sewer Utility Project Update
Week of June 13th
The contractor completed water main installation and continued sanitary sewer installation along 15th Avenue between 15th Street and 17th Street; they continued sanitary sewer installation along 17th Avenue between 16th Street and 17th Street, and they replaced several water service laterals along 16th Avenue between 25th Street and 26th Street.
Week of June 20th
The contractor will begin hooking up residences to the new water main along 15th Avenue between 16th Street and 18th Street; they will continue storm sewer work along 15th Avenue between 15th Street and 18th Street; they will continue sanitary sewer work along 17th Avenue between 16th Street and 18th Street, and they will continue water service lateral work and place concrete sidewalk at various locations throughout the City.
PLEASE NOTE
For residents living within an active work zone and participating in the City’s bulk pick-up the week of June 20th, please place your items in the middle of your driveway. This will allow the contractor to complete any grading or underground work that may be necessary to your home. For more information on the bulk pick-up, please refer to the City’s web page: https://menominee.us/department-of-public-works-city-engineer/.