Week of July 25th
The contractor installed water main along 15th Street between 14th Avenue and 17th Avenue; they installed a storm sewer along 16th Avenue between 17th Street and 18th Street; they staked for concrete curb and gutter along 15th Avenue; they completed miscellaneous removals along 15th Avenue and 17th Avenue, and they completed water service replacements along 16th Avenue.
Week of August 1st
The contractor will continued storm sewer installation along 16th Avenue between 15th Street and 17th Street; concrete curb and gutter will be poured along 15th Avenue and 17th Avenue, and they will continue water service replacements along 16th Avenue.
PLEASE NOTE:
- We understand this project has been an inconvenience for many residents and businesses in and around the construction area. The contractor is working diligently to maintain access at intersections, but there are many operations that create unknown or hazardous conditions so complete access is not always possible. Public safety is always on the forefront so please drive around the project area if possible, or utilize the alleys. For those who need to navigate through the construction zone, please use caution and take your time when driving.
- For residents living within the project area, please have your garbage/recyclables placed at the end of your driveway no later than 7:00 AM on Monday mornings. GFL continues to work directly with the contractor to coordinate this pick-up as early as possible to minimize any disruption in the active work zone. If your garbage/recyclables are placed at the end of your driveway after pick-up has occurred, your items will not be picked up that week and everything will be placed in front of your house outside the grading limits