City of Menominee – State Revolving Fund Water & Sewer Utility Project Update
Week of July 11th
Contractor completed removals along 16th Avenue between 14th Street and 16th Street and along 15th Street between 14th Avenue and 16th Avenue; they completed storm sewer installation along 15th Avenue between 15th Street and 16th Street and at the 17th Avenue / 17th Street intersection; they started staking for concrete curb and gutter at the intersections of 15th Avenue / 18th Street and 17th Avenue / 18th Street; and they completed water service replacements along 17th Street.
Week of July 18th
Contractor will continue to fine grade and place base aggregate along 15th Avenue and 17th Avenue; they will continue removals along 16th Avenue between 16th Street and 18th Street and along 15th Street between 15th Avenue and 17th Avenue; they will begin underground work along 16th Avenue and 15th Street; and they will continue water service replacements at various locations throughout the City.
PLEASE NOTE
- For residents living within the project area, please have your garbage/recyclables placed at the end or your driveway no later than 7:00 AM on Monday mornings. GFL is working directly with the contractor to coordinate this pick-up as early as possible to minimize any disruption in the active work zone. If your garbage/recyclables is placed at the end of your driveway after pick-up has occurred, your items will not be picked up that week and everything will be placed in front of your house outside the grading limits.
- As work continues, please be aware of continuously changing conditions and traffic access. If you are access to an alley, please utilize that as much as possible. If your only access is along the roadway under construction, it is not uncommon for your access to change multiple time throughout the day or even be restricted for a short duration depending on the contractor operations. Please be patient as the project progresses.