City of Menominee – State Revolving Fund Water & Sewer Utility Project Update

Week of August 8th

The contractor finished installing the water main along 16th Avenue and is now completed for the project; the crew installed a sanity sewer main along 16th Avenue between 14th Street and 16th Street; the crew installed water services and sanitary sewer laterals along 16th Avenue; crew installed storm sewer along 16th Avenue between 16th Street and 17th Street; they graded for sidewalk and driveway approaches along 15th, and they completed water service replacements to several homes along 16th Avenue.

Week of August 15th

The contractor will continue storm sewer installation along 16th Avenue between 14th Street and 15th Street; the crew will continue sanitary sewer main installation along 16th Avenue between 15th Street and 18th Street, and the crew will begin forming and placing concrete sidewalk and driveway aprons along 15th Avenue and 15th Street.

PLEASE NOTE

  • As the concrete sidewalk and driveway aprons are poured, please stay off them for at least 7 days to allow the concrete to fully cure.