City of Menominee – State Revolving Fund Water & Sewer Utility Project Update

Week of August 15th

The contractor continued to install sanitary sewer and storm sewer along 16th Avenue between 16th Street and 18th Street; crews installed water services and sanitary sewer laterals along 16th Avenue; crews poured the concrete curb and gutter along 17th Avenue, and crews started forming sidewalk and driveway aprons along 15th Avenue.

Week of August 22nd

The contractor is expected to finish sanitary sewer main and storm sewer main installation along 16th Avenue; they will pour concrete sidewalk and driveway aprons along 15th Avenue and 15th Street; they will grade the roadway along 16th Avenue, and they will grade and form sidewalk and driveway aprons along 17th Avenue.

PLEASE NOTE

As the concrete sidewalk and driveway aprons are poured, please stay off them for at least 7 days to allow the concrete to cure fully.